cotton gin civil construction

civil construction

Stripes was contracted to complete the Civil & Concrete Foundations for the new Carroll Cotton Gin facility which commenced in 2020.  Project works included bulk excavation earthworks for the two gin basements and building footings, detailed earthworks, installation of 1800m³ of concrete including core filled basement walls, 70T steel reinforcement and 80 pier anchors.  

 

Additional works completed while on site included:

  • Supply & Installation of Services including Stormwater, Compressed Air & Washdown Water and assistance with Hydraulic Piping Installation
  • Supply & Installation of Fire System including two fire water tanks, pump, fire water ring main piping, hydrants and associated fixtures in line with AS2419
  • Supply, Fabrication & Installation of MCC Switchroom Building
  • Supply, Fabrication & Installation of RMU Support Structure  

Scope of Project

Date

2020-2021

client

Carroll Cotton Co

Location

carroll